Gantt chart for tasks
|
|
======================
|
|
|
|
The goal of this Gantt chart is to display a time based overview of the tasks for a given project.
|
|
|
|
- The Gantt chart is available from the "view switcher"
|
|
- Only project managers can access this section
|
|
|
|

|
|
|
|
- The **start date** and the **due date** of tasks are used to draw the chart
|
|
- Tasks can be resized and moved horizontally with your mouse
|
|
- There is no vertical drag and drop
|
|
- The bar is the same color as the task
|
|
- Each bar display a progression status in percentage, this percentage is calculated by using the column position on the board
|
|
- To fit with the Kanban model, tasks can be ordered by the board positions or by the start date
|
|
- New tasks created from this view will be displayed on the board at the position 1 in the first column
|
|
- Tasks are displayed in black when there is no start or due date defined
|
|
|
|

|